Case Studies

Engineering outcomes for real production environments

Engineering examples from real production environments

These examples show the type of reliability, maintenance and improvement work DEVA Maintenance Services delivers across manufacturing, industrial and commercial environments. Client names can be kept confidential where required.

Featured Case Study

Stainer Dosing Machine Reliability Improvement & External Filter Access Upgrade

Before

Stainer dosing machine before the upgrade — full overview showing canisters, dense hoses and lower-mounted components with poor access
Stainer dosing machine before the upgrade — close-up of heavily contaminated hoses, fittings, filters and red-handled valves buried beneath the canisters

After

Stainer dosing machine after the upgrade — angled view showing accessible stainless pipework and rows of relocated red-handled valves
Stainer dosing machine after the upgrade — front view showing the relocated external filter and valve arrangement across the lower front

Overview

DEVA Maintenance was brought in to investigate and improve a stainer dosing machine that had suffered ongoing reliability issues from new. Persistent blockages, pipe bursts, overflows and inaccurate dosing were creating repeated faults and making routine maintenance difficult.

The project focused on redesigning the filter and valve access arrangement, carrying out remedial repair work, and restoring the machine to a cleaner, more serviceable and more reliable condition ready for recalibration and production use.

The Challenge

The machine had suffered repeated faults including stainer blockages, pipes bursting, overflows, incorrect dosing quantities and dried stainer build-up within the system.

A major root cause was poor accessibility. The strainers, filters and ball valves were positioned directly underneath the canisters/tanks, making them extremely difficult to access, inspect and clean. Because servicing these components was awkward and messy, routine maintenance was not being carried out as effectively or as regularly as required. This contributed to contamination and restrictions within the pipework, leading to recurring blockages, pressure-related failures and poor dosing accuracy.

The DEVA Solution

  • Designed a new external filter and valve access arrangement within limited available space
  • Relocated the strainers, filters and ball valves from underneath the canisters to an accessible external position
  • Installed high-pressure-rated suction and pressure lines
  • Thoroughly cleaned the system to remove blockages and dried stainer build-up
  • Replaced 4 pumps
  • Replaced 4 canister stirrer motors
  • Bench tested the remaining stirrer motors
  • Stripped and cleaned multiple fittings and non-return valves
  • Completed full installation and on-machine testing
  • Water tested the system for leaks before handover

Once the mechanical work and testing were complete, the machine was handed back to production for calibration using their stainer product, ready for return to service.

The Result

The completed work significantly improved serviceability and access for routine inspection and cleaning. Moving the filters and valve arrangement to the outside of the machine made future maintenance much easier, cleaner and more practical.

More projects

More Projects & Site Improvements

Shorter examples of engineering, safety and improvement work delivered on live production sites.

Silo walkway after treatment — freshly applied dark anti-slip coating providing grip in wet and powder-contaminated conditions
Site Safety & Remedial Works

Silo Walkway Anti-Slip Safety Improvement

A practical, fast-deploying anti-slip treatment for a silo access walkway that had become hazardous in wet and dusty conditions — now being rolled out to further walkways across the site.

View Case Study
Bespoke mobile shadow board for production line change parts — organised tool and change-part storage with labelled silhouettes, mounted on a wheeled stainless frame for point-of-use positioning during changeovers
Continuous Improvement & OEE

Production Line Changeover & 6S Improvement Project

A practical 6S and changeover improvement project within a high-volume manufacturing facility — bespoke mobile shadow boards brought tools and change parts to the point of use, reducing search time and supporting faster, more repeatable changeovers.

View Case Study
Ballcock control cam assembly after repair — cleaned shaft, cam collars and limit switches reset to their correct operating positions
Breakdown Maintenance & Fault-Finding

Ballcock Control Cam Timing Repair

Control cams that had fallen out of sequence were causing product overflow and switch contamination. The assembly was stripped, cleaned, re-timed and tested, with permanent reference marks added for quicker future calibration.

View Case Study
Recent work

Selected engineering case studies

Food Production-60% downtime

60% reduction in line stoppages

Implemented a planned preventative maintenance schedule and reliability programme across two filling lines, reducing unplanned downtime by 60% over six months.

Paint Manufacturing+16 pts OEE

OEE lift from 58% to 74%

Loss analysis and targeted engineering improvements on a high-volume dispensing line. Quick wins delivered in week one, sustained improvement over 12 weeks.

Paint Manufacturing-35% changeover

35% reduction in changeover times

Structured SMED approach and tooling improvements on a paint factory coating line, cutting batch changeover downtime by over a third.

Furniture ManufacturingOn-time delivery

Successful 5-day shutdown delivery

Provided a multi-skilled engineering crew for a planned annual shutdown — mechanical and electrical scope completed on time and on budget.

Industrial Processing200+ assets

PPM system rollout across 200+ assets

Built an asset register, condition-based maintenance schedule and task documentation. The site moved from reactive to planned-led maintenance inside one quarter.

AgricultureZero repeat faults

Conveyor reliability programme

Identified developing failures through structured inspections; remedial works eliminated repeat breakdowns on a key throughput conveyor.

Commercial FacilitiesMulti-site cover

Contract maintenance cover

Provided ongoing planned and reactive engineering cover across a multi-site commercial portfolio. Single point of contact, predictable cost.

Need Engineering Support? Let's Discuss Your Requirements.

Speak to a DEVA engineer about reducing downtime, improving reliability or supporting your next shutdown.